Full scaffold wrapped around the building with pedestrian protection at the North Elevation.  Included a full "dance floor" at the 4th floor level to move materials and debris from all elevations to the South east lower corner where the drumpster was placed.

Work included:

  • Removal of existing Stucco cladding

  • Shear wall repairs at multiple elevations including existing plywood removal, installation of new framing members, Shear Wall panels to bring the building up to code compliance

  • Installation of new Windows, Sliding Glass Doors, French Doors, and Deck Doors.

  • Installation of new Deck Lighting, Roof Lighting, Security Lighting

  • Installation of new Hose bibs and Water Shut Off Valves at the Roof

  • Installation of new DuroLast Roofing and Under Protection Board including Scuppers, Through Wall Scuppers, and Termination Bars

  • Installation of new Trespa Composite Siding

  • Installation of new James Hardie Artisan Shiplap Siding

  • Installation of new James Hardie Soffit Board at all decks/overhangs

  • Installation of new Bryer Sheet Metal Siding and Accessories

  • Installation of new DensElement sheathing for Weather Resistive Barrier with DensDefy Liquid Applied Flashing

  • Installation of new Insulated Vinyl Siding at West Elevation for Noise Reduction due to Highway 99 Traffic

  • Installation of new Building Signage

  • Installation of new Pecora Deck Coating System at all decks, walkways, and concrete covered decks.

  • Installation of new Aluminum Handrail systems by American Railworks at all decks

  • Installation of new Sherwin Williams Durations Paint

  • Rework of existing Handrails Systems which included sanding, dent repairs, replacement of glass, and full painting

Project Details:

  • Location: Seattle, WA

  • Architect/Consultant: Evolution Architects

  • Final Contract Amount: $3,734,230